Full control cabbing installation works associated with two new 2 stage trans-critical CO2 plants.

Booker Food Logistics

Project Details:

PCI were engaged to carry out full control cabbing installation works associated with two new 2 stage trans-critical CO2 plants at Booker Food Logistics in Royton, Oldham.

The works consisted of safe isolation and removal of existing systems in the following areas:

  1. Freezer Chamber (-22°C)
  2. Airlock (+10°C)
  3. Marshalling (+1°)
  4. Poultry (+1°)
  5. Chill 1 & 2 (+1°)

 

The works were carried out over a staged period to avoid and disruption to the depot’s day to day operations.

Following the removal of the existing system new services were installed by PCI as below:

  • Control Panels
  • Full containment system and supports
  • Cabling & terminations to following:
    • Fans
    • Dampers
    • De-frost systems including peripheral heaters
    • Temperature probes
    • Valve station controls
    • RDM systems
    • CO2 detection wiring
  • Testing & Commissioning
  • O&M manuals